CINEMA GREEN - Where do we stand?
the situation is this:
Contract in September 2006: € 705,304 amount
With special supplementary report has already been granted the firm a variant of € 141,055
The company has stopped the work and then demanding money and other damages.
To avoid legal action for damages has been approved a further transaction in favor of the company € 88,000.
The amount thus increased from € 705,304 to 934,359, an increase of 32.4%
Perhaps the work will start again. Maybe. Meanwhile there are already nearly three years.
But this is the system to manage contracts?